2. Chairman Ford welcomed our guest, Jerry
Cawthon.
3. The minutes of our meeting on September
21, 2005 were presented. A motion was made by Danny Everett and seconded
by Travis Beach to approve as read. Approved unanimously.
4. Staff and Committee Reports
· Sewer Project Update - John Gentry
The monthly status report #12 covering the month of August 2005 was
reviewed noting that the retainage has been increased from 5% to 10%
due to unsatisfactory progress of the project and possible construction
liens against QPS. We are meeting on a two-week basis now due to various
construction issues. Liquidated damages will occur if QPS fails to meet
the extended deadline of December 18, 2005. We anticipate Keaton Beach
going on-line in mid to late November. The pumping station is near completion
and the septic issue has been resolved. We have submitted for approval
PPE#12 to which we will apply the balance of our OTTED funds ($34,791.23).
We have a submittal for $26,674 EPA funds pending receipt. To date,
we have $443,254.96 in our Construction Funds Account.
QPS receives 80% of the contract amount
with JEA receiving the other 20%. JEA has been submitting monthly invoices
at approximately $11,728 and now tell us that they are "short-changed".
They propose billing at $17,000 per month for the next 4-6 months beyond
the current contract completion date of 9/10/05. Contingency funds are
being depleted by these additional costs. We will negotiate with JEA
and discuss the proposed liquidated damages against QPS.
JEA will verify that QPS vendors have
been paid in full and give notice of such to TCW&SD before the final
payment is made to QPS and the contract closed.
· Financial Reports - Diane Carlton/Shirley
Shinholser
Diane Carlton reviewed the Directors Report dated 9/30/2005 (total receivables
$10,090.62). Past due notices were mailed last month and several accounts
have been paid. We have sent a certified letter to Hugh Poppell and
will turn his water off if he does not pay. We will send a letter to
Mrs. Crowder at the address Glenn Senter will provide in an attempt
to obtain payment on that past due amount of $330.51. Historically,
Bowden and Buckhalter have paid "lump sum" amounts and failed
to notice that their credits have been exhausted. We will contact them
again.
Shirley Shinholser reviewed the September
balance sheet noting that monies in the Membership Checking Account
have been redistributed per Board precedents of 4/2003 and 1/2004. Fifty
percent (50%) of the monies have been applied to our Loan at Citizen's
Bank (remaining balance of $9,983.74 due 6/17/05); 25% has been placed
in Savings, Capital Improvement Funds; and the remaining funds, excluding
a minimal amount of $89.30, have been placed in Savings, Cash Reserve
to be used on an "as needed" basis by TCW&SD per Board
approval. Our 25% Pre-Planning Grant for Phase 2 expense of $4,675 will
be paid with funds in Savings, Cash Reserve as previously approved.
Our September 2005 Profit/Loss indicates a loss of $7,639.01 which includes
our FMHA Interest expense paid to RD on September 1. Actually, our monthly
loss was $292.01. An expense breakdown is provided.
Since Water Rate Scenario "D"
adopted 9/21/05 could not be implemented into our RVS system due to
so many increment breakdowns, we asked RCAP to create Scenario "F"
with adaptations to accommodate our billing system. Rates from Scenario
"F" correspond with rates from Scenario "D" for
385 of our 414 customers. The remaining rates increase slightly due
to increment changes increased from 3,000 gallons to 6,000 gallons.
Overall, Scenario "D" generates $186,415.20 and Scenario "F"
generates $187,064.40, an increase of $649.20. A motion was made by
Travis Beach to adopt Scenario "F" as a replacement for previously
adopted Scenario "D". A second was received from Glenn Senter
and the motion was approved unanimously.
· Management Issues - John Gentry
A letter has been prepared and sent to Annette Wright of the Taylor
County Planning and Zoning Board regarding our proposed $2,000 service
fee. We have asked that this information be included in the packet given
to developers noting that water is available for a fee which must be
paid before the application can be considered complete. We will send
a second letter defining lots versus units and fees required for potential
redevelopments that may require extra water service beyond what is already
established per lot.
We have prepared a list of those desiring
Grinder Pumps outside the grant program. We have requested an updated
QPS estimate so that we can prepare letters to these customers and request
pre-payment for the GP installations. Once the payment is received,
we will issue a request for the installation. All septic tanks in the
coastal zone are to be decommissioned and customers must connect if
sewer/water service is within 200' of their property. In the future,
TCW&SD will solicit bids and sub-contract the installations and
TCW&SD will provide all grinder pumps - not the customers. The cost
of future connections is yet to be determined.
Sandra Bolton has submitted her resignation
as Billing Supervisor of TCW&SD effective 9/30/05.
A December party will be discussed at the November meeting and plans
will be made to recognize Sandra's faithful service of 10+ years.
Will we continue to have Annual Meetings
since we are no longer incorporated? Board will revisit this issue in
November.
· Operational Issues - Jim Gooding
Jim Gooding presented a prepared hand-out to be given to all contractors
regarding the minimum specifications required by TCW&SD for pipe
and meter installations and proposed that the Board adopt it as a standard.
A motion was made by Travis Beach and seconded by Lonnie Houck to adopt
the document as a minimum requirement standard. Approved unanimously.
The required DEP samples have been submitted
and we are working on the Emergency Response Plan that is due by December
2005. The new sign for the WTP is in place and looks great. We inventoried
our stock in September 2005 and are working to develop more formal records.
· Phase II Funding - Floyd Ford
We sent a letter to Representative Kendrick regarding the State Revolving
Funds and why we chose to seek government grants instead. No response
has been received yet. JEA over 50% complete with the Preliminary Engineering
Report (PER) and the field work is complete for the Environmental Assessment
(EA). We should receive the documents for review within 2-3 weeks. The
CBIR is in process and will be completed soon so that we can send it
to the State Legislature.
5. Old Business
· Update Taylor County contact on
installation of Fire Hydrants - John Gentry
This was in the approved budget of TCBCC but we have not been advised
of any action. I will contact Kenneth Dudley again.
· Update of proposed District O&M
Building - John Gentry
The paperwork for the lease of the building currently being used by
QPS is in process. TCW&SD will take ownership when QPS vacates.
The fence, storage containers, etc. offered by QPS contained a 15% overhead
and $6,700 seems too high for used equipment with some known leaks.
If we can save any funds here, we can use them elsewhere. We might look
at renting a storage trailer. Limerock has been brought in at an approximate
value of $2,000.
· Sign - Glenn Senter
I attended the Technical Review meeting and will be put on the agenda
for the Building and Planning meeting on December 3, 2005. If denied
again, I will approach TCBCC.
· Update on court order for installation
of GP on Timothy Brooks' lot - Floyd Ford
A court order has been issued and we are waiting for Mr. Brooks' reply.
· Hiring of WWTP Operator - John
Gentry
Mac Odom has been release due to conflicts regarding insurance coverage
and consistent misunderstandings about the work requested/desired. We
have approached Danny Lundy, recently retired from the City of Perry,
but he is not really interested although he is willing to help out in
an emergency. I'm speaking with William Conrad from Tallahassee about
an operator. John Ola with US Water Services is being asked to provide
a proposal on operation and emergency services for the Plant and/or
Grinder Pumps.
· Foundation tie-down for District
Building - John Gentry
Jim and I have inspected the District Building and determined it to
be of better construction and more secure than first thought. We feel
that we can bolster the nailing and add some ground anchors (perhaps
double what we have) all around. Danny Everett will prepare a quote
on some 5' anchors and feels that a concrete surround will not be needed.
· Recommendations for Commissioners
Board was reminded to give this careful attention so that recommendations
can be made to TCBCC in a timely manner. Recommendations are to be presented
at the November meeting.
6. New Business
· Cost of living increases for employees - Floyd Ford
Floyd Ford issued a proposal that TCW&SD commit to a 5% wage increase
for John Gentry, Jim Gooding, and David Morgan to be effective with
wages received on or after January 1, 2006 since they have not had a
pay raise for 2-3 years. He further proposes that TCW&SD commit
to raising the wages of the other employees effective January 1, 2006
per the National index and establish a policy to give a cost of living
raise per the National index each year thereafter to all employees.
Travis Beach set the proposal to a motion; seconded by Danny Everett
and approved unanimously.
· Discussion of proposed Sewer Rate
- Floyd Ford
Scenarios 1 and 2 as prepared by RCAP were presented to the Board for
review. We will have a Public Hearing at our next meeting on November
16, 2005 to establish the new rate.
· David advised the Board that he
did not pass his Class C Sewer Operator test and will have to retest
in February 2006.
7. Motion to adjourn was made by Travis
Beach; second by Danny Everett. Meeting adjourned.
(The next meeting is scheduled for Wednesday,
November 16th, at 5:00.)
Board Actions: 1. Adopt Scenario "F"
as the new water rate structure.
2. Adopt a Minimum Requirement Standard for Pipe and Meter Installations.
3. Approve a 5% wage increase for John Gentry, Jim Gooding, and David
Morgan and a cost of living raise per the National index for the other
employees to be effective with wages on or after January 1, 2006.
4. Establish a policy that employees receive a cost of living raise
per the National index each year.
Action Items: 1. Pursue installation of fire hydrants.
2. Pursue lease of QPS building and all modifications needed.
3. Pursue tie-downs for District Building.
4. Consider Board member recommendations.
John K. Gentry, P.E.
General Manager
|